YMCA Parking Lot Concrete Overlay – Oshkosh, WI

Project Overview

Located on 20th Street in Oshkosh, WI, the YMCA parking lot renovation project consisted of a 214,000 square foot fiber-reinforced concrete overlay, requiring more than 3,400 cubic yards of ready-mix concrete. The overlay design was critical to the overall success of the project.

Challenge: Stormwater Regulations & Parking Capacity

Exposing the aggregate base beyond a specified square footage would have triggered a full stormwater review, which in this case would have required a retention pond, catch basins, and landscape islands.

These additions would have eliminated nearly 50 parking stalls, an unacceptable outcome for the owner.

The only alternative to preserve parking capacity would have been installing an underground stormwater containment system, a significantly more expensive solution.

Technical Requirements & Engineering Solutions

Tight tolerances were required near the building, where maintaining existing curb heights was essential. Through careful engineering and layout adjustments, the Milis team achieved proper drainage at less than 1% slope while preserving all curb elevations, successfully overcoming one of the project’s primary technical challenges.

Cost Savings & Long-Term Performance

The overlay provided substantial cost savings over a full asphalt replacement while offering superior longevity and minimal maintenance. With only one access point and hundreds of daily facility users, phasing was critical. The Milis team maintained continuous facility operations without long-term shutdowns and completed the project on schedule, demonstrating the efficiency and practicality of concrete overlay systems.

YMCA's Testimonial

“We had the pleasure of working with Milis Flatwork on our recent parking lot project, and we couldn’t be happier with the experience. We chose Milis because they are a local company that demonstrated a genuine passion for our project. Their team was incredibly patient and attentive, truly listening to our needs and concerns throughout the entire process.

Opting for concrete over asphalt was an important decision for us, as we wanted a durable solution with sustainability benefits. The challenges we faced, particularly the constant flow of traffic in and out of our parking lot, could have been overwhelming. However, the Milis team excelled in maintaining constant communication with our staff, allowing us to remain operational while minimizing disruption for our members.

The end result has been a major improvement for our facility that has thrilled both our members and staff. The enhanced visibility and brightness of the new parking lot have truly uplifted the entire space. We are grateful for our members’ patience and flexibility during the project, as we worked together to create an outstanding environment for our community to enjoy for generations to come.

Thank you, Milis Flatwork, for your hard work and dedication!”

– Angie Flanigan | YMCA